Oregon Construction Contractors (CCB) Practice Test

Disable ads (and more) with a membership for a one time $2.99 payment

Prepare for the Oregon Construction Contractors Exam with our comprehensive study resources. Utilize flashcards and multiple-choice questions, each equipped with hints and detailed explanations, to ensure exam success. Start your practice today!

Each practice test/flash card set has 50 randomly selected questions from a bank of over 500. You'll get a new set of questions each time!

Practice this question and more.


What is the safest approach when estimating labor and materials for projects?

  1. Using a variety of estimation methods

  2. Relying solely on experience

  3. Applying the least time-consuming method possible

  4. Only using quantity take-off method

The correct answer is: Using a variety of estimation methods

Using a variety of estimation methods is the safest approach when estimating labor and materials for projects because it incorporates multiple perspectives and techniques, which can lead to a more balanced and accurate estimate. Different methods can provide insights into various aspects of the project, such as costs, time requirements, and resource allocation. This multi-faceted approach allows estimators to verify assumptions, identify potential oversight, and adapt to different project scales and complexities. By leveraging diverse estimation methods—such as unit cost estimation, detailed quantity take-offs, and historical data analysis—contractors can cross-check their estimates for consistency and reliability. This reduces the risk of underestimating or overestimating costs, which can lead to budget overruns or resource shortages during the course of a project. Meanwhile, relying solely on experience can introduce bias and overlook new trends or changes in material costs and labor rates. An approach focused on speed may sacrifice accuracy, while using only one specific method, like the quantity take-off, may not capture the comprehensive picture needed for more complex projects. Therefore, employing a variety of estimation methods is a sound strategy for enhancing the accuracy and effectiveness of project estimates.