Which of the following is NOT part of the Project Closeout process?

  1. Inspecting completed work

  2. Finalizing documentation

  3. Posting formal notice of site safety rules

  4. Conducting a final walkthrough

The correct answer is: Posting formal notice of site safety rules

The Project Closeout process involves several key activities focused on ensuring that all aspects of the project are finalized and documented correctly. Inspecting completed work, finalizing documentation, and conducting a final walkthrough are all essential tasks that help confirm that everything has been completed as per the project specifications, that all necessary paperwork is in order, and that the client is satisfied with what has been delivered. Posting formal notice of site safety rules, however, is generally related to the initial stages of a project and ongoing safety management rather than project closeout. During this phase, the emphasis is on completing the project, ensuring compliance with all contractual obligations, and transitioning the project to the client or end-user. Therefore, this task would not typically be included in the closeout process, making it the correct answer in this context.